The Soquel Drive Buffered Bike Lane & Congestion Mitigation Project is making excellent progress toward its Spring 2025 completion. When it's done, we'll enjoy enhanced safety for cyclists and pedestrians thanks to buffered and protected green bike lanes and more visible cross walks. Traffic congestion should also improve considerably with the installation of adaptive smart lights along Soquel Drive. The lights will be better synchronized and also be able to talk to the buses, ensuring faster transit service.
Since the project began, crews have made significant progress, including:
• Completing 65 out of 95 ADA ramps
• Nearing 75% completion of sidewalk construction
• Finishing two of the eight retaining walls
• Installing approximately 3 miles of fiber optic conduit for the Adaptive Traffic Signals
Upcoming activities are scheduled across multiple locations on Soquel Drive between La Fonda Avenue to State Park Drive including the installation of ADA ramps, sidewalks with retaining walls, landscape restoration, fiber optic infrastructure for the adaptive traffic signals, rectangular rapid flashing beacons crosswalks, and more.
The Soquel Drive Buffered Bike Lane & Congestion Mitigation Project aims to
To view the full project schedule, please go here.